The Class 3 estimate is where most capital project decisions are made — it's the "approved budget" number that management carries into execution. Get the methodology right from the start.
How Kpex implements Class 3 following AACE 18R-97
Kpex 2G guides the cost engineer through every step of the Class 3 workflow — from scope input to indexed, location-adjusted output — enforcing the AACE recommended methodology at each stage. The platform validates inputs, applies the correct indices automatically, and generates a documented Basis of Estimate aligned with AACE 18R-97.
The Class 3 Budget (or Preliminary) Estimate is produced when engineering is 10–40% complete — typically at the conclusion of FEED or early detailed engineering. It carries an expected accuracy of −20% to +30% and is the estimate that most organisations use for budget authorisation and capital appropriation.
It is the most consequential estimate in the capital project lifecycle. Once a Class 3 is approved, the project moves from study to execution — resources are committed, contracts are placed, and the organisation is accountable to the number.

At Class 3, the cost model is built on a hierarchical Work Breakdown Structure (WBS) with four levels of decomposition:
| Level | Name | Example | Cost Type |
|---|---|---|---|
| L1 | Facility | Methanol Plant | Rollup |
| L2 | Area | Area 100 — Feed Handling | Rollup |
| L3 | System / Unit | Unit 101 — Methane Reformer | Rollup |
| L4 | Cost Item (leaf) | 101-H-001 Reformer Furnace | Unit cost entry |
Only Level 4 items carry direct cost — all higher levels are computed by rollup. This structure enables granular control, clear accountability by area, and meaningful variance analysis during execution.
Build the four-level hierarchy based on the project's P&IDs (30–60% complete), plot plan, and scope definition document. Each L4 item corresponds to a discrete, priceable work package or cost element.
For each L4 item, determine the quantity from engineering deliverables: vessel weight, pipe length, concrete volume, cable length, instrument count, valve count, etc. At Class 3, quantities may be interpolated from P&IDs or estimated from plot plans where detailed takeoff is not yet available.
Price each L4 item using unit costs from a validated cost database. Kpex Module A provides equipment unit costs; construction unit costs (civil, piping, E&I) come from in-house history or published estimating references (Richardson's, Means, Norsok).
For disciplines not fully detailed yet (electrical, instrumentation), apply discipline factors as a percentage of the major equipment or process piping cost. These factors are validated against historical project data in the Kpex benchmarking database.
Add project indirect costs using percentage factors or detailed breakdowns:
Apply the Z.4 Location Factor for geographic adjustment and the Z.5 Cost Adjustment Index for time escalation between the cost basis year and mid-point of construction. Convert to the project reporting currency.
Apply contingency at the L1 level using a risk-based approach (Monte Carlo or parametric). At Class 3, typical contingency ranges 10–20% of the pre-contingency estimate. Management Reserve (for unknown unknowns) is held separately by the owner.
The BoE is as important as the number itself. It documents every assumption, exclusion, reference, and adjustment factor — enabling the estimate to be reviewed, updated, and defended through the project lifecycle.
| Dimension | Class 4 | Class 3 |
|---|---|---|
| Engineering complete | 1–15% | 10–40% |
| Cost basis | Equipment list × factor | Four-level WBS + unit costs |
| Accuracy range | −30% / +50% | −20% / +30% |
| Contingency | 15–25% | 10–20% |
| Primary use | Concept comparison, FEED go/no-go | Budget appropriation, contract strategy |
| P&ID status | Preliminary / process flow | 30–60% issued for review |